DISPLAY HOME
PROJECT
















 
WEEK 6

First full week for three weeks with no Public Holidays but poor weather moves in again slowing
construction. Most windows are installed and weatherboard stops are fitted in one day.
Work continues inside avoiding rain showers, with internal walls straightened, showerbase cut
outs, and ceiling battens installed. Weatherboard cladding continues to go on when weather
breaks, and construction of the framework for the verandah is also completed.
 

Windows and weatherboards started
 
Walls straightened - rough in - verandah
 

Ceiling battens and insulation


         