DISPLAY HOME
PROJECT
















 
Bearers and joists laid
 


WEEK 2
With the stumps completed, bearers and joists were laid (Day 8),
work continued on the brick work in the garage in readiness for
the trusses to be erected, which were finished by the end of the
week.Floor insulation, heating ducts and some sub floor plumbing
was fixed prior to floor insulation and flooring being laid.
Wall frames were marked out on the floor in preparation for
erection next week.

 

Ready for sub-floor plumbing
 
Flooring
 
Garage trusses erected