DISPLAY HOME
PROJECT
















 
Completed rear deck
 



WEEK 13
This week a lot of the internal finishing jobs are tackled so that the
painters are able to finish off the inside of the home. Fretwork is fitted, shelving is hung and vanities installed. Waterproofing to the bathroom
and ensuite is carried out in preparation for tiling. Steps are
constructed and fitted to the front and rear entries of the home.

Meanwhile, the painters begin painting the outside of the home
choosing to start on the timber windows and trims around the doors.
With most of the kitchen cupboards fitted on Day 89, whilst the
electrician puts in a fair effort to install the 52 down lights chosen
as lighting for the home. A monitored alarm system is also
completed and activated to protect the contents.

 

Balustrade to verandah fitted
 
Internal fretwork fitted
 
Kitchen Started