Kit home suppliers - modular kit homes - steel frame kit homes kit houses


Kit Home suppliers





DISPLAY HOME
PROJECT
















 
Set out and slab poured
Bricks delivered
 


WEEK 1
With a building permit being issued a week earlier than expected,
it was a bit of a mad rush for David to reschedule trades so work
could commence. Due to the size of the block, the Garage was the
first to start, with a slab being poured on Tuesday (Day 2), and brick
work for the boundary walls and framing starting on Thursday (Day 5).
Mega Anchor stumps went in on Friday (Day 5), with all 61 stumps
being installed in one day.

 

Frames on garage
 
Brickwork commenced
 
Stumps in